Press Releases - August 2004

 

 

 

ENVIRONMENTAL ANALYSIS FOR COMPLETION OF THE 241 TOLL ROAD RESULTS IN MORE THAN 6,000 LETTERS AND CARDS

IRVINE, Calif. . (August 13, 2004) - The 90-day public review period for the Foothill-South Draft Environmental Impact Statement (EIS) and Subsequent Environmental Impact Report (SEIR) yielded more than 6,000 comment letters on 10 project alternatives to address growing traffic congestion in South Orange County. Included in the 6,000 plus comments letters and cards are approximately 169 letters that will be reviewed and responded to in the Final EIS/SEIR.

"The amount of comments we received is a clear sign that our efforts paid off to make this document as accessible as possible -- online, on CD, and in print," said Macie Cleary-Milan, TCA Deputy Director of Environmental Planning. "Over the next few months, we will carefully review and respond to the comments, prepare the final document, and continue to work closely with the federal resource agencies to determine a preferred alternative in early 2005."

The 3,200-page Draft EIS/SEIR, released May 7, analyzes the potential environmental, socio-economic, and traffic impacts of six toll-road alignments to extend the 241 south from its current end at Oso Parkway and four non-toll road options -- the widening of Interstate 5 by two general purpose lanes, the widening of major city roads, and two 'no project' scenarios.

At the June 19 public hearing at Tesoro High School 198 people made oral comments to two court reporters.

In May, the Foothill/Eastern Board of Directors, which operates the 241, 261, and 133 Toll Roads, extended the public comment period to 90 days, twice the legal requirement of 45 days.

Next Steps

Comments on the Draft EIS/SEIR will not be responded to individually, but over the next six to nine months, will be compiled and incorporated into a "Response to Comments" document as part of the Final EIS/SEIR. TCA will continue to work with the Federal Highways Administration, Army Corps of Engineers, U.S. Fish and Wildlife Service, Environmental Protection Agency, Marine Corps Camp Pendleton, and Caltrans on narrowing the alternatives and selecting a preferred alternative.

Two decisions must be made before construction can begin. The FHWA, as the lead agency for the federal environmental regulatory process, and the Foothill/Eastern TCA Board of Directors, comprised of 15 city council members and County Supervisors from areas along the 241, 261, and 133 Toll Roads, must certify the Final EIS/SEIR and select a preferred alternative.

If the FHWA and the Foothill/Eastern TCA select a toll-road alternative, the TCA will obtain final regulatory permits and obtain a FHWA Record of Decision. If a ROD is obtained in 2005, construction can begin around 2006-2007, with a completion date of 2008-2009. If a non-toll road project alternative is selected, such as the I-5 or arterials-only widening options, the TCA would not be responsible for permitting or building the project.

Anticipated FTC-S Schedule, subject to change:

  • August to December 2004 -- Review and respond to comments received
  • First Half 2005 -- Release of Final EIS/SEIR. Foothill/Eastern Transportation Corridor Agency Board of Directors chooses a locally preferred alternative and certifies the SEIR. Obtain necessary permits from U.S. Fish and Wildlife Service, Army Corps of Engineers and EPA.
  • Second Half 2005 -- Federal Highway Administration (FHWA) approves the EIS and issues a Record of Decision on a preferred alignment. Obtain Coastal Commission Permit. Finalize finance plan and obtain financing
  • 2006/2007 -- Begin construction.
  • 2008/2009 -- Open to traffic.

Project History

The southern extension of the 241 Toll Road, the final piece of Orange County's network of public toll roads, has been the subject of regional planning efforts since 1981. A conceptual highway, then named the Foothill Transportation Corridor, along the inland foothills of south Orange County was placed on Orange County's Master Plan of Arterial Highways (MPAH). The highway was planned as a regional alternative to the I-5 Freeway to handle traffic from new housing developments in southern and eastern Orange County and increasing regional traffic between San Diego and Los Angeles.

In 1991, the Foothill/Eastern Agency selected a preferred alignment for the 241 extension. Since then, a change to the federal environmental regulations required the Agency to embark on a new federal review process. Since 1999, TCA in conjunction with state and federal agencies have determined a Statement of Purpose and Need and identified 10 project alternatives to address traffic in South Orange County.

About TCA

More than 290,000 trips are taken on The Toll Roads every weekday, saving drivers an estimated 21 minutes per trip. The Toll Roads are operated by the Transportation Corridor Agencies, two joint powers authorities formed by the California state legislature in 1986 to plan, finance, construct, and operate Orange County's 67-mile public toll road system. Fifty-one miles of the system are complete, including the 15-mile San Joaquin Hills (SR-73) Toll Road from Newport Beach to San Juan Capistrano; and the 36-mile Foothill/Eastern Toll Road system (SR-241, SR-261, SR-133) from the 91 Freeway to south Orange County. More information including maps, toll rates, news, and FasTrak, the non-stop, electronic toll-payment system, can be found at www.thetollroads.com.

 

 

   

 

   
 FasTrak Customer Service (800) 378-TRAK (8725) | The Toll Roads Walk-In Service Center
125 Pacifica, Ste. 120, Irvine, CA 92618 | Transportation Corridor Agencies | (949) 754-3400
FasTrak(R) is a registered TCA trademark. | Copyright © Transportation Corridor Agencies
All rights reserved. Click here to see our privacy policy.